1. Identify Your Mixing Tank Configuration
Mixing tank package is an optional upgrade. C, A, and X Series chambers generally do not include the mixing tank package as standard. Without this upgrade, the chamber has a solution reservoir for premixed solution. Prepare and verify the solution separately before adding it to the reservoir. Follow the filling and mixing instructions below only if the mixing tank package is installed.
Use only the operating procedure for the package installed on your chamber. The presence of a touchscreen does not mean that filling and mixing are controlled by the touchscreen; the relevant features must be installed.
| Installed configuration | How water is filled | How mixing starts and stops | Go to |
|---|---|---|---|
| C Series manual mixing tank | Operator opens and closes the water-fill valve | Operator opens and closes the mixing-air valve | Section 3 — Manual C Series |
| PC-controlled mixing tank | PC software operates the installed water-fill valve | PC software operates the air sparger; mixing timer available | Section 4 — PC controls |
| Touchscreen-controlled mixing tank (with installed outputs) | Touchscreen manual controls operate the installed fill valve | Touchscreen manual controls operate the sparger | Section 5 — Touchscreen |
What is a sparger? It is the air-distribution device at the bottom of the solution reservoir. Bubbles rising through the solution provide agitation. On controller-operated equipment, the software starts and stops the installed electrically operated valves; the physical supply valves normally remain in their correct operating positions.
2. Prepare the Reservoir and Ingredients
- Confirm that no test is drawing from the reservoir while a new batch is being prepared.
- Inspect the reservoir for cleanliness and any remaining solution or rinse water. Account for residual liquid in the batch calculation.
- Determine the amount of solution required and measure the appropriate water and ingredients according to the test method.
- Prepare any ingredient that must be dissolved separately, in accordance with the recipe.
- Confirm that the required water and compressed-air supplies are available.
The solution reservoir described in the CCT-NC manual has a nominal capacity of 60 US gallons. Use the actual intended batch quantity rather than assuming the tank contains that volume.
Concentration example: A nominal 5% sodium chloride solution by mass contains 5 kg sodium chloride and 95 kg water in 100 kg of finished solution. Follow the applicable procedure for exact concentration, water quality, salt grade, pH, and measurement conditions.
3. C Series — Manual Mixing Tank Package
This section is for the manual C Series mixing tank package only. The operator opens and closes the water and air valves physically. The touchscreen does not control these mixing tank functions.
Fill the Solution Reservoir
- Locate the manual water-fill valve on the mixing tank.
- Open the valve to begin adding water.
- Observe or measure the quantity entering the reservoir.
- At the required quantity, close the water-fill valve manually.
- Confirm that water has stopped flowing.
Stay with the reservoir while filling. The overflow connection is not a substitute for closing the valve.

Add the Ingredients
- Confirm that the planned quantity of water has been added.
- Add measured ingredients in the sequence required by the solution recipe.
- Add any separately dissolved ingredients as directed; leave enough room for air agitation without excessive splashing.
Mix the Solution
- Locate the manual mixing-air valve.
- Gradually open the valve to admit air to the sparger.
- Check for bubbles rising through the solution; adjust the air valve until the liquid mixes effectively without excessive splashing.
- Continue mixing until the ingredients have dissolved and the solution is uniform.
- Close the mixing-air valve manually and verify bubbling has stopped.

Manual shutoff: This configuration has no controller mixing timer or controller-operated shutoff for these functions. Close both manual valves when their operations are complete.
Continue to Section 6 — Verify the Finished Solution. Do not follow the PC or touchscreen procedures.
4. PC-Controlled Mixing Tank Package
This section is for a mixing tank with installed PC-controlled filling and mixing. Use software to start and stop routine operations. The physical supply valves need to be correctly positioned, not opened and closed for every batch.
Check Water and Air Supplies
- Verify that the DI-water supply is available and the mixing tank water-fill supply valve is open.
- Verify the compressed-air supply is available and the mixing-air adjustment valve is open enough to permit effective sparger agitation.
- If the physical valves are already correctly positioned, leave them in place for routine operation.
The mixing-air adjustment valve can be used to regulate agitation. Open it sufficiently for mixing without excessive splashing.
Fill the Reservoir With the PC
- Open the chamber control software.
- From MAIN MENU, open Status of Current Test.
- Find Mixing Tank Fill and click the switch to ON.
- Monitor the water entering the tank. For a partial batch, measure the required quantity and turn Mixing Tank Fill OFF at that quantity.
- For filling to the full-level indication, the normal PC fill function stops water flow when the reservoir full-level switch is activated.
- Verify that filling has physically stopped before adding ingredients.
The full-level indication is not a recipe measurement. Do not use it to estimate the water needed for a partial batch. Monitor the actual volume or mass required.


Add the Ingredients
- Confirm water filling has stopped.
- Add measured ingredients in the required sequence, including any separately prepared additions.
- Allow sufficient space for agitation.
Set the PC Mixing Timer
- From MAIN MENU, open Adjust Machine Parameters.
- Under Timers and Cycle Feature Setup, locate Mix Tank Sparger Time.
- Enter the desired duration in seconds; complete any required password entry and save the setting.
| Mixing duration | Enter in timer |
|---|---|
| 15 minutes | 900 seconds |
| 30 minutes | 1,800 seconds |
| 60 minutes | 3,600 seconds |
| 90 minutes | 5,400 seconds |
Start and Stop Mixing With the PC
- Return to MAIN MENU → Status of Current Test.
- Click Mixing Tank Sparger ON.
- Check that bubbles rise through the liquid and provide adequate agitation.
- Allow the timer to expire, or click Mixing Tank Sparger OFF to stop earlier.
- Verify that the mixing output is OFF and bubbling has stopped. If ingredients are not fully dissolved, run an additional mixing interval.
With normal operation, there is no need to close the physical mixing-air adjustment valve after each batch.
Continue to Section 6 — Verify the Finished Solution. Skip the touchscreen procedure.
5. Touchscreen-Controlled Mixing Tank Package
Use this section only if the tank-fill and mixing-air outputs are installed and connected to the touchscreen. An ordinary C Series touchscreen does not automatically provide these features.
Check Water and Air Supplies
- Confirm that the DI-water supply is available and the mixing tank water-fill supply valve is open.
- Confirm that compressed air is available and the mixing-air adjustment valve is open sufficiently for mixing.
- If these valves are correctly set, use touchscreen controls for routine starting and stopping; do not repeatedly operate the physical valves.
Fill the Reservoir Using the Touchscreen
- Confirm that no test cycle is running.
- Select MAIN MENU → MANUAL CONTROL.
- Press NEXT to reach Manual Operation Page 2.
- Press SLT TNK FIL OFF to turn the fill output ON.
- Monitor the actual quantity of water added. When it reaches the amount required, press the fill control again to turn it OFF.
- Verify that water has physically stopped flowing.
Manual-control filling: When commanding the fill output directly from the touchscreen manual-control screen, monitor the tank and stop filling yourself. Do not rely on automatic level protection in the normal fill sequence as a substitute for observing manual operation.

Add the Ingredients
- Confirm filling is OFF.
- Add the measured ingredients in the sequence required by the recipe, including separately prepared additions.
- Allow space for adequate agitation.
Mix Using the Touchscreen
- Press PREV to return to Manual Operation Page 1.
- Press MIX AIR OFF to turn on the solution tank sparger.
- Observe the reservoir and verify that bubbles produce adequate mixing. Adjust the physical mixing-air adjustment valve only if the airflow needs correction.
- Continue mixing until the ingredients are dissolved.
- Press the mixing control to turn it OFF if it is still running, and verify bubbling has stopped.
The touchscreen manual-control pages have a timeout. When the preset interval expires, manually activated outputs turn OFF (except the cover), and the screen returns to the menu. If more mixing is required, return to MANUAL CONTROL and turn MIX AIR ON again.
Optional: Operate Mixing During a Running Test
The touchscreen also has a separate MIX button on the test monitor. This operates the installed sparger while a test is running; it is not required for preparing a new batch before testing.
- On the test monitor, press MIX and verify the display indicates MIX ON.
- Allow the timed interval to finish, or press the button again to stop earlier.
- Set the interval using MIXER TIME under MACHINE SETUP. This setting is in minutes; the manual gives a factory preset of 90 minutes.

Continue to Section 6 — Verify the Finished Solution.
6. Verify the Finished Solution
Perform these checks regardless of which mixing tank configuration you have. Air agitation helps dissolve and distribute ingredients but does not establish compliance with a solution specification.
Inspect and Measure the Solution
- Confirm that water filling and air mixing have stopped.
- Inspect the tank for undissolved ingredients and check that the solution appears uniform. Mix longer if needed.
- Measure the concentration, pH, temperature, and any other parameters required by the applicable test procedure, using the specified methods and conditions.
Correct and Recheck if Needed
- If results are outside the specified limits, make only those adjustments allowed by the applicable procedure.
- Mix the corrected batch thoroughly.
- Repeat the necessary measurements and verify the solution is acceptable before testing.
Complete the Batch
- For the manual C Series package, verify the manual water-fill and mixing-air valves are closed.
- For a controller-operated package, verify the fill and mixing outputs are OFF and the actual flows have stopped.
- Replace the reservoir cover and record the batch date, quantity, ingredients, and required verification results.
Ready for use: A mixing timer ending or a reservoir reaching its full indication does not establish that the solution is correct. It is ready when the applicable test requirements are met.
7. Troubleshooting
| Problem | Likely cause or check | Action |
|---|---|---|
| No water enters — manual C Series | Water unavailable or manual water-fill valve closed | Check water supply and manual valve |
| No water enters — controller-operated | DI supply unavailable; supply valve closed; controller output OFF; reservoir already full | Verify supply, valve position, controller indication, and level |
| Water continues after controller fill is OFF | Fill valve or controls may not be shutting off | Safely isolate the water supply and arrange service |
| No bubbles — manual C Series | No air supply or manual mixing-air valve closed | Verify air supply and gradually open mixing-air valve |
| No bubbles — controller-operated | No air supply; mixing-air adjustment valve restricted; output OFF | Verify supply, valve position, and controller indication |
| Mixing stops early — PC | Mix Tank Sparger Time elapsed | Check timer setting and repeat mixing if needed |
| Mixing stops during touchscreen manual control | Manual-control timeout elapsed | Return to MANUAL CONTROL and activate MIX AIR again |
| Excessive splashing | Airflow too high | Reduce sparger airflow with the mixing-air adjustment valve |
| Ingredients remain undissolved | Insufficient agitation or time; recipe sequence issue | Check recipe and continue mixing as appropriate |
| Concentration or pH out of range | Incorrect batch calculation; residual liquid; incomplete mixing | Recalculate, make permitted corrections, mix, and retest |
Safety: Do not bypass electrical controls or protective devices. If flow continues when a controller output is OFF, safely isolate the affected supply and obtain service.
8. Manual Reference
Source: Auto Technology CCT-NC Training Manual, Rev. 5.2 (April 2023). Relevant material includes the solution reservoir and water/air components, touchscreen MANUAL CONTROL (Section 4.4.5), PC Status of Current Test (Section 4.6.4), and PC mixing timer setup.
Equipment configurations and installed options vary. Match the screenshots and physical components to the supplied chamber documentation. References in this guide identify valves by purpose rather than their schematic numbers.
For neutral salt spray solution measurements, see ASTM B117 Salt Solution: Concentration. Use the concentration and pH limits in the method specified for your test.